Client: Riviera Utilities

List of Completed Projects:
Project/Contact Tasks Project Management

Fairhope 115/13.2 kV Substation
(2008-2010)

Tom DeBell
(251) 943-50001
Gary Carnley
(251) 626-5000

Engineered new 115/13.2 kV distribution station with one transformer, circuit switcher, low-side bank breaker and four feeder regulated bay.

Grading and permitting, Physical, Relay and Control Design. We secured Control House and panels, managed construction and commissioned the station.

Eastern Shore 230/13.2 kV Substation
(2009-2010)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Engineered new 115/13.2 kV distribution station with one transformer, circuit switcher, low-side bank breaker and four feeder regulated bay.

Grading and permitting, Physical, Relay and Control Design. We secured Control House and panels, managed construction and commissioned the station.

Spanish Fort 115 kV Switching Station
(2007-2008)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Engineered new 115 kV Delivery Point with three 115 kV main substation feed. The project involved breaker protection, 115 kV metering and 115 kV PTs and station service.

Grading design, Physical, Relay and Control Design. We secured materials through packager, managed construction and commissioned the substation.

Spanish Fort 115/13.2 kV Substation
(2007-2008)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Engineered new 115/13.2 kV distribution station with two transformers, circuit switchers, low-side bank breakers and a five feeder regulated bay.

Physical, Relay and Control Design. We secured materials through packager, managed construction and commissioned the substation.

Daphne 115/13.2 kV Substation
(2006-2007)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Engineered new 115/13.2 kV distribution station with two transformers, circuit switchers, low-side bank breakers and a five feeder regulated bay.

Physical, Relay and Control Design. We secured materials through packager, managed construction and commissioned the substation.

Beasley 115/13.2 kV Substation
(2008)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Engineered second 115/13.2 kV distribution transformer, circuit switcher and low-side bank breaker.

Relay and Control Design. We fabricated and secured protection panels and commissioned the station.

Belforest 115 kV Switching Station
(2008)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Replaced a 115 kV breaker and its protection panel.

Relay and Control Design. We fabricated the protection panel and commissioned the breaker.

Southwest Foley 115 kV Switching Station
(2008)

Tom DeBell
(251) 943-5001
Gary Carnley
(251) 626-5000

Replaced a 115 kV breaker and its protection panel.

Relay and Control Design. We fabricated the protection panel and commissioned the breaker.